Reconstruction of a Bridge over Łososina in Dobra
Country: Poland, Dobra
Project value: 1250000
Type: Roads and Bridges
Project status: Concluded
Description
The Investment included:
- Reconstruction of a bridge over Łososina, km 47+800.00 + 929.60 of the National Road No. 28:
- Disassembly of abutments and wings to the level of ca. 0.7 m below the upper edge of the pier caps.
- Reconstruction of abutments along with the strengthening of the foundation.
- Renovation of pillars along with the strengthening of the foundation and the capping beams.
- Renovation and strengthening of the WBS beams.
- Strengthening of the existent deck - an overlay.
- Renovation of steel bearings.
- Construction of a temporary bridge km 47+811.00 over the Łososina river, with two-way traffic along with access roads in km 94+935.50 of the National Road No. 28 and its subsequent disassembly upon the completion of the reconstruction of the bridge over Łososina.
- Disassembly of the pavement structure along the National Road No. 28.
- Pavement milling along the National Road No. 28.
- Construction of a left-side sidewalk and a right-side sidewalk of the width of 1.7 m.
- Construction of a new pavement structure.
- Construction of an overlay along the National Road No. 28.
- Execution of slope stairs for the maintenance team.
- Stabilization of the Łososina banks.
- Execution of a drainage system for the facility and construction of treatment devices.
Customer:
GDDKiA Kraków
Contract Value:
5 000 000 PLN / 1 250 000.00 EUR
1 EUR = 4.00
Year:
08/2008 – 09/2009