Modernization and Expansion of the Sewage System for the City of Jaworzno – Arrangement of the Sewage Management System in the Basins of the Following Rivers: Biała Przemsza and Przemsza”

Country: Poland, Jaworzno Project value: 4375000 Type: Others Project status: Concluded
Description

The object of the investment is the construction of a sanitary sewage system along with the reconstruction of pavement in the Góra Piasku and Długoszyn housing complexes as well as in ul. Wolności. The entire project aims at the improvement of the sewage system within the city of Jaworzno, reducing contaminants evacuated to the water and soil as well as at general improving the quality of the physical settings.

 

The project included the construction of:

  • sanitary sewers  Ø 200mm – Ø 315 mm ,
  • headers Ø 160 mm  to the boundary
  • sanitary sewage pumping station
  • lift station with pipes

 

Construction of the sewage system in a road lane results in the necessity to reconstruct the pavements of streets and sidewalks upon the completion of works, in the places where sewers are located. The street, sidewalks, and dirt roads shall be reconstructed in accordance with the design of the road.

 

Basic Parameters

  • Length of gravity sewers Ø 315mm – 200mmm -  22 301 linear meters, PVC pipes
  • Headers Ø 160 to the estate – 4347 linear meters, PVC pipes
  • Manholes Ø 1000 – 612 items
  • Manholes Ø 600 – 196 items
  • Manholes Ø 400 – 841 items
  • Sewage pumping station - Góra Piasku – 1 item - with a forced sewer, diameter: 110 mm, length: 415.3 m, PE pipes  
  • Sewage pumping station - Osiedle Długoszyn – 4 items -  with a forced sewer, diameter:1967 mm , PE pipes 

 

Customer:

Miejskie Przedsiębiorstwo Wodociągów i Kanalizacji Sp. z O.O. Jaworzno

Contract Value:

17 500 000 PLN / 4 375 000.00 EUR
1 EUR = 4.00

Year:

11/2011 – 07/2013