Design and construction of the S19 road from the Białystok Południe junction (no junction) - Ploski

Project value: 0 Type: Roads and Bridges Project status: Concluded
Description

The task entrusted to Mota-Engil assumes the execution of design works and then the construction of two roads with two lanes in each direction, as well as the reconstruction of roads colliding with the planned expressway and the construction of service and access roads. The section also includes the Zabłudów junction, which will provide a Białystok - Zabłudów - Bielsk Podlaski - Juchnowiec Kościelny relation. The task will also include the construction of 16 engineering structures: 8 road viaducts, 4 bridges, including a 160-meter high bridge over the Narew River. There will also be 4 crossings for animals. The new road will be equipped with road traffic safety, environmental protection and drainage and lighting systems.

 

The investment will be carried out in the "Design and build" system, and the task will be completed within 36 to 39 months (during the implementation period excluding winter, i.e. from December 16th to March 15th). The construction works were planned for 2022-2024.

 

The planned section S19 Bialystok-Ploski is part of the planned international Via Carpatia route, an investment of European importance, connecting the Baltic States with Southern Europe. It is also a very important route for the inhabitants of Bielsko Podlaskie, connecting the city with Białystok.

 

ORDER VALUE:
396 981 704.99 PLN

 

TASK:
Construction of the S19 section Białystok Pd-Ploski

 

LONG:
12.73 km

 

SYSTEM:
Design & Build

 

IMPLEMENTATION DEADLINE:
36-39 months
2022-2024

 

CLIENT:
GDDKiA Białystok Branch

 

CONTRACTOR:
Mota-Engil Central Europe S.A.