Construction of an Interchange along the National Road No. 7 in Mogilany, km 680+100.62 and Access Roads to the Facility
Country: Poland, Mogilany
Project value: 4625000
Type: Roads and Bridges
Project status: Concluded
Description
Comprehensive execution of an interchange including:
- construction of interchange connectors, channelized junctions and service roads
- reconstruction of the district road and the National Road No. DK 7, involving its extension and changing the structure of its pavement
- execution of drains under the road and “French-type” drains
- disassembly of the old overpass and construction of a new one (length: 67 m) – prestressed, beam and slab structure suspended with hangers on steel arches
- construction of culverts and retaining walls
- slope stabilization with stone mattresses
- trade works dealing in the reconstruction of the telecom network, the power network, the gas piping, the water supply system and the lighting; additionally: execution of illumination of the bridge structure.
Basic Parameters /Podstawowe Parametry
- Theoretical span - 50 m (a single-span overbridge)
- Total span – 68.2 m
- Total width – 17.4 m
- Load class: A in accordance with PN 85/S - 10030
- Overbridge built for the National Road No. 7, km 680 + 100.62
(GP-class road) along a district road (Z-class road)
Customer:
GDDKiA Kraków
Contract Value:
18 500 000 PLN / 4 625 000.00 EUR
1 EUR = 4.00
Year:
08/2010 – 08/2012