Mota-Engil Central Europe has completed the construction of 11.3 km of the S3 expressway section from the Lubin Północ junction to the Lubin Południe junction. All works were carried out according to the schedule within 30 months.

 

As part of the task, the company built two road junctions – Lubin Zachód and Lubin Południe and made 9 engineering structures in reinforced concrete technology. There were also 12 access roads for local traffic created. The route built by the contractor bypasses the city of Lubin from the west.

 

– The implementation of our part of the investment, but also the entire route running from the north to the south of the country, will reduce travel time and improve road safety. It is difficult to imagine, that it can further improve the investment attractiveness of the region, because Lower Silesia is a well-recognized area by the business and like only few others – cares about its development. For sure, the development of road infrastructure in this part of the country, will relieve the main arteries, and this is the undoubted value of this investmentsays Piotr Bienias, Board Member of Mota-Engil Central Europe. – Part of S3, which is being delivered today, is one of the two investments we have carried out in this region. We will soon have another investment finalization, this time S3 Jawor-Bolków – he adds.

 

  • Investment in the "design build" system
  • 11.3 km of a new two-lane road
  • Increased transport accessibility of the region, improvement of a road safety
  • Complicated works in mining damage areas
  • Contract value: PLN 260 903 266
  • Period of execution: 26.01.2015 – 15.06.2018
  • Client: GDDKiA Wrocław
  • Contractor: Mota-Engil Central Europe