MECE's Electromechanical Department will expand and modernize the 220/110 kV Rożki substation

23-08-2022
MECE's Electromechanical Department will expand and modernize the 220/110 kV Rożki substation

We are about to execute another contract for Polskie Sieci Elektroenergetyczne S.A. 

 

MECE Electromechanical Department will expand and modernize 220/110 kV Rożki substation. All work will be carried out on the active facility in temporary arrangements, so as not to disrupt the operation of the National Power System. 

 

The investment plans include:  

 

  • dismantling of the existing and construction of a new 220 kV switchgear, 
  • modernization of secondary circuits, telecommunications, SOT, 
  • construction of a technology building including an access road,  
  • construction of three buildings of own needs,  
  • reconstruction of autotransformer stations, 
  • reconstruction of line inputs to the substation. 

 

The investment is of key importance for the security of the electric power system of the whole country, including the Radom area in particular. The investment will improve operating conditions and affect the safety and reliability of electricity transmission.  

 

The value of the contract is more than PLN 120 million, and its completion is scheduled for late 2025 and early 2026.