Fajny Dom phase IV
Fragment of a residential and service complex, composed of two residential 5-storey buildings with garages on the ground floor (H1-H2), located along the Łęgówka stream.
The H1 and H2 buildings were designed in the square-like top view, with the disc and slab frame made in the RCC technology, filled with walls made from medium-sized hollow brick, with a circulation core in the center, which stiffens the structure. Flats are located on upper floors (from storey 1 upwards), while the ground floor holds the entrance zone with technical rooms and utility rooms, plus individual closed garages accessible from the street level. Walls on the ground floor - at the main entrance to the buildings - designed in a concrete brick cladding (chopped texture). Other external walls plastered (render coating); colour: cream with grey fragments (balcony tiling).
The concept provides for compositional separating of the ground floor and vertical plates in the building corners with plaster of contrasting colouring (chocolate brown).
1.Number of underground floors | 0 |
2.Number of overground floors | 5 |
3.Ground floor level | +0.00= 199.65 above sea level |
4.Total floorage | 1,966.62m² |
5.Floorage | 1,633.06m² |
6.Floorage – utility rooms and technical rooms | 43.62m² |
7.Floorage – circulation spaces - staircases and entrance enclosures with halls | 184.71m² |
8.Floorage - garages | 199.04m² |
9.Floorage - flats | 1,205.69v |
10.Internal cube | 6,201.00m³ |
11.Number of flats | 28 |
12.Number of residents | 60 |
13.Number of parking spaces in the garage | 12 |
Customer:
Sołtysowska Project Development Sp. z o.o.
Contract Value:
7 712 065 / 1 928 016.25 EUR
1 EUR = 4.00
Year:
04/2013 – 06/2014