Electrical Substation Sochaczew
The expansion of the station includes a number of activities related to the
construction of new elements and the modernization of existing ones.
The contract includes:
• wexecution of detailed and as-built documentation for the
Project, along with conducting public communication activities,
• expansion of the 220 kV switching station and construction of
the 220/110 kV transformation,
• modernization of the existing stormwater drainage network to
increase capacity, including replacement of the oil separator,
• modernization of the system of internal roads to the possibility of
building access benches to the newly constructed station,
• construction of 400 kV fields and connection to 400 kV line
Chelm-Lublin Systemowa,
• construction of a relay building and a building for own needs,
• construction of a new AT1 autotransformer stand,
• construction of a 110 kV cable line to connect the existing
autotransformer unit AT2 with field No. 2 of the 110 kV switchgear,
• delivery, installation and commissioning of SOT systems, as well
as telecommunications work.