Construction of the S1 expressway Kosztowy - Bielsko-Biała Section II Junction
The consortium of PORR S.A. and Mota-Engil Central Europe S.A. will carry out the contract for the construction of the S1 Kosztowy - Bielsko-Biała expressway Section II "Oświęcim" junction (with the junction) - Dankowice in the "design and build" system. The Contractor is to prepare the design documentation and obtain all necessary conditions, agreements, opinions, permits and administrative decisions allowing for the realization of the investment and road execution. The task is to be completed in 33 months, excluding winter periods during the execution of the Works.
CLIENT: GDDKiA Warszawa
CARRYING OUT THE PROCEEDINGS: GDDKiA Katowice branch
CONTRACTOR: The consortium PORR S.A. & Mota-Engil Central Europe S.A.
Signing a Contract: 14.05.2020 r.
Contract completion date: 14.08.2023 r.
Contract Value: 989 751 443,10 PLN (gross)
System: design & build
Location: 12+865 km - 28+030 km
SCOPE OF WORKS
ROADS:
- construction of the S1 express road about 15,2 km long;
- 3 road junctions: Oświęcim, Wola, Brzeszcze
- reconstruction of existing roads in the field of collision with
the S1
- construction of access roads
- construction of emergency crossings and emergency
entries
- construction of sidewalks
- construction of surface and deep water drainage systems,
- construction of road culverts,
- construction of traffic safety devices
BRIDGES:
- 10 objects along the planned S1 expressway
- 5 objects crossing the planned S1 expressway
- 2 railway viaducts
- 1 upper passage for large animals
- 7 ecological culverts
BRANCHES:
- Lighting
- Traffic lights
- Power network
- Greenery and logging
- Acoustic and anti-glare screens
- Demolition works
- Teletechnical network
- Technological channels
- Rainwater drainage and cleaning devices
- Sanitary sewage
- Water supply network
- Gasnetworks
- Construction of retention and retention-infiltration reservoirs
- Road Marking
- Fencing
- Traffic Management System