Complete the S3 expressway from the Kaźmierzów interchange to the North Lubin interchange
Project value: 0
Type: Roads and Bridges
Project status: Concluded
Description
Client: GDDKiA
Leader: Mota-Engil Central Europe S.A.
Partners: MASFALT Sp. z o.o., DROGOMEX Sp. z o.o.
Duration: 12 months, excluding winter periods from December 23 to March 15
End date: second quarter of 2021
Length: 14,4 km
Contract value: approx. 228,4 million PLN
Approximately 25% of the work foreseen in the original contract remains to be done. It should include complete the construction of the express road (on the Kaźmierzów - Polkowice section, 2 roadways with 2 traffic lanes and emergency lanes, while on the Polkowice - Lubin North section, 2 roadways with 3 traffic lanes and emergency lanes) and the junctions Kaźmierzów, Polkowice and Lubin North. Construction of 25 engineering facilities, drainage systems and environmental protection equipment are also to be completed.
Source: GDDKiA